Zoning and land use

Landmarks Preservation Commission approval

If a building is a landmark or sits in a historic district, LPC approval comes before any DOB permit. Here are the three permit types and what each covers.

What work needs Landmarks Preservation Commission approval?

Quick Answer

Any exterior work on an individual landmark or on a building in a historic district, and interior work at an interior landmark. The Commission issues three levels of permit depending on the scope, and its approval has to come before the Department of Buildings will issue a construction permit for the same work.

Discretionary approvals

Who does this land on?

Owners and buyers of brownstones and buildings in historic districts, commercial tenants installing storefronts and signage, and anyone whose renovation schedule assumes a single agency.

What governs it?

  • The Landmarks Law in the Administrative Code, which designates landmarks and historic districts and requires a permit for regulated work
  • The Landmarks Preservation Commission, which issues the permits and holds hearings on the larger ones
  • The requirement that a Landmarks permit precede a Department of Buildings permit for the same work
  • The distinction between staff-level permits for work meeting stated criteria and Commission-level review for work that does not
  • The separate Zoning Resolution provisions that allow transfers of development rights from landmark sites

How does the process run?

  1. Confirm the status first: individual landmark, interior landmark, scenic landmark, or a building inside a historic district
  2. Scope the work and identify what is visible from a public thoroughfare, because visibility drives the review level
  3. Where the work needs a Department of Buildings permit but has no effect on the significant protected features, seek a certificate of no effect at staff level
  4. Where the work affects protected features but needs no Department of Buildings permit, seek a permit for minor work
  5. For anything altering the protected features beyond what staff may approve, apply for the Commission-level approval, which involves a public hearing and a vote
  6. Take the Landmarks permit to the Department of Buildings and file the construction application against the approved drawings
  7. Build to the approved drawings exactly, because a departure is enforceable by Landmarks separately from the Department of Buildings

Where does it bite in a transaction?

  • A renovation budget and schedule assume one agency and one permit
  • A storefront or sign is installed without Landmarks approval and has to come down
  • Windows are replaced in kind on paper and in a different profile in fact
  • A closing is scheduled around a Department of Buildings permit that cannot issue until Landmarks acts

Does Landmarks review interior work?

Only at a designated interior landmark, which is a separate and much narrower category than a historic district. In an ordinary historic district building, the Commission regulates the exterior. Work with no exterior effect in such a building is a Department of Buildings matter, subject to the usual codes.

Which permit level applies to your work?

It follows the scope, and at staff level the Department of Buildings permit is the dividing line. Work that needs a Buildings permit but has no effect on the significant protected features takes a certificate of no effect; work that affects protected features but needs no Buildings permit takes a permit for minor work; anything beyond what staff may approve goes to the Commission with a public hearing. Scope creep moves the file between levels.

How does landmark status affect development rights?

A landmark site is usually under-built relative to the district, and the Zoning Resolution has a specific mechanism permitting a transfer of the unused development rights, by special permit and with limits on where they may land. It is a public review process, and it is the main way landmark status turns into value.

What else should you read before you file or sign?

Zoning and land use

Have a closing coming up?

Tell us about the transaction. An attorney reads every intake form and responds the same business day.

Legal Disclaimer: This page is general information about New York practice. It is not legal advice, it does not account for the terms of any particular contract, building or transaction, and reading it does not create an attorney-client relationship. This is attorney advertising. Prior results do not guarantee similar outcomes.