AC · §28-302.4
Report of critical examination.
This section requires a registered design professional to submit a written report to the commissioner within 60 days after completing a critical examination of exterior walls. The report must document conditions, including deterioration and watertightness, and be signed by the design professional. Applies to building owners undergoing critical examinations.
Summary by Nacmias Law Firm — for general information. The official statute text on AmLegal controls.