§ 27-951 Inspections and tests.
AC § 27-951
(a)Inspections. Every new system and every part of an existing system that is altered, extended, renovated, or repaired, except for ordinary repairs, shall comply with the applicable requirements of this subchapter.
(b)Notification. Advance notification of tests and inspections required by this section shall be given to the commissioner.
(c)Representation at test. Tests required by this section shall be conducted in the presence of the commissioner or his or her authorized representative, or in lieu thereof, the commissioner may accept a signed statement of an architect or engineer, whose name is submitted with the notification in subdivision (b) of this section, declaring that he or she has witnessed the tests and that the standpipe system meets the requirements of this code. If a representative of the commissioner does not appear within two days after receipt of such report by the commissioner, the report shall be deemed to be accepted by the commissioner.
(d)Testing equipment required. All equipment, material, and labor required for testing a system or part thereof shall be furnished by, and at the expense of, the person responsible for installing the work.
(e)Testing of system. Systems may be tested in sections, or parts, in accordance with the requirements of this subchapter.
(f)Acceptance. Before the acceptance of such system, each system shall be subjected to the tests required by this section.
(g)Standpipe system tests.
(1)PRESSURE TESTS. a. The test shall demonstrate that the system will sustain a hydrostatic pressure of at least one hundred psig, and at least three hundred psig at the siamese connection, for a period of at least one hour at the topmost hose outlet and at the lowest fire pump supply connection to the system. In buildings not exceeding three stories or forty feet in height, the test pressures need not be more than fifty psig. in excess of the normal hydrostatic pressures at the topmost hose outlet, and this pressure must be maintained for a period of at least one hour. b. Pressure tanks shall be tested to demonstrate that they will sustain a hydrostatic pressure of at least one hundred fifty per cent of the normal maximum required operating pressure for a period of at least one hour.
(2)FLOW TEST. The system shall be flow tested to determine that water is available at the top outlet of each riser, the lowest outlet in each riser, and through each siamese connection. The system shall be flushed to remove all foreign matter from the system. Flow shall be through at least a two and one-half inch hose without nozzle at each one of the above mentioned locations at separate times.
(3)ALTERATION TESTS. When alterations, additions, or repairs are made to a standpipe system, the entire system shall be subjected to a hydrostatic test pressure of at least fifty psig at the highest hose outlet, and in addition, a flow test shall be made as stated in paragraph two of this subdivision through the new or altered portion of the system.
(h)Pump tests.
(i)Test equipment for fire pumps.