1114.4.1 Grit chamber.
PC § 1114.4.1
All drywells shall contain a grit chamber as part of the drywell system. Grit chambers shall be constructed in accordance with the following requirements: 1. Solid access cover with a minimum diameter of 15 inches (381 mm).
2.Grit chamber designed to support the maximum anticipated load.
3.Outlet invert elevation shall be a minimum of 1 inch (25 mm) lower than the lowest inlet elevation.
4.The sump shall be a minimum of 18 inches (450 mm) or two times the largest inlet pipe diameter, whichever is greater, as measured to the outlet invert elevation.
5.The interior dimensions shall be a minimum of 18 inches (450 mm) or four times the largest inlet pipe diameter whichever is greater.