3305.8.7.5 Verification by special inspector.
BC § 3305.8.7.5
No construction load shall be placed on a floor or portion of a floor until the temporary or permanent decking for the floor or such portion is in place and the cold-formed steel special inspector required by Chapter 17 has verified compliance with Section 3305.8.6, including but not limited to the drawings required by Section 3305.8.6.1. At a minimum, this special inspection shall be performed at least once for each floor. In addition to the documentation required by Chapter 17, the special inspector shall document the verification in accordance with the checklist required by Section 3305.8.8. (Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023) Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2023/077.