3305.3.3.2.1 Intervals.
BC § 3305.3.3.2.1
Formwork shall be observed at intervals permitting observation of representative configurations throughout the project duration. The formwork designer shall maintain a log of such observations at the construction site. At a minimum, observations shall be made: 1. Immediately after formwork related incidents or violations are issued; and 2. When concrete construction operations are significantly modified such as changes to form materials, concrete placement cycle, or form and support layout prior to use of the change.