1619.3.4 Permit renewal for temporary construction installations that utilize an action plan.
BC § 1619.3.4
Where a temporary construction installation requires an action plan in accordance with Section 1619.5, the application to renew the permit for such temporary construction installation shall be accompanied by the submission of a report from a registered design professional certifying, based on an inspection of the temporary construction installation performed by the registered design professional within 30 days prior to the submittal of the permit renewal application, that the action plan: 1. Is still in effect; 2. Has been revised to reflect the current conditions of the temporary structure; or 3. Is no longer required, as the temporary structure has been retrofitted to comply with the loads for new construction without any reduction, pursuant to Section 1619.3.2.