What is NYC AC § 28-112.2.2?

Quick Answer

This section outlines the fee structure for permits required for electrical work, specifying that 50 percent of the total fee must be paid at the time of filing, with the remainder due before any departmental inspection. Applies to building owners seeking permits for electrical work.

General informational summary. Not legal advice for your situation. Consult an attorney before acting on any specific matter.

Michael Nacmias - Founding PartnerMichael Sargo - Partner
From the team atNacmias Law Firm, PLLCBrooklyn-based attorneys representingproperty owners across all five boroughsMeet the team →

§ 28-112.2.2 Permits for electrical work.

AC § 28-112.2.2

Fees for electrical work requiring a permit shall be in accordance with department rules. For electrical work requiring a permit, 50 percent of the total fee for the work permit, but not less than $130, or the total fee for the work permit where such fee is less than $130, shall be paid at the time of filing, and the remainder of the total fee shall be paid before any department inspection. (L.L. 2024/128, 12/21/2024, eff. 12/21/2025) Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2024/128.

Common Questions

Our team

Meet the people you will work with

Free case review

Have a matter that touches § 28-112.2.2?

Free 15-minute case review with the attorney handling your matter. Same-day response during business hours across all five boroughs — OATH hearings, Housing Court, and real estate closings.

Or email us

[email protected]

An attorney reads every message.

  • Same-day response

    During business hours

  • Direct attorney access

    Same lawyer from intake to close

  • Flat-fee pricing

    On most OATH and closing matters