What is NYC RCNY § 1-111?

Quick Answer

The following clean-up requirements shall be followed during the conduct of abatement activities on asbestos projects: (a) (1) All waste generated shall be bagged, wrapped or containerized immediately upon removal. The personal and waste decontamination enclosure systems and floor and scaffold surfaces shall be HEPA v

General informational summary. Not legal advice for your situation. Consult an attorney before acting on any specific matter.

Michael Nacmias - Founding PartnerMichael Sargo - Partner
From the team atNacmias Law Firm, PLLCBrooklyn-based attorneys representingproperty owners across all five boroughsMeet the team →
Effective: 1/6/2019Last amended: 1/6/2019

§ 1-111 Preliminary Clean-up Procedures.

RCNY § 1-111

The following clean-up requirements shall be followed during the conduct of abatement activities on asbestos projects: (a) (1) All waste generated shall be bagged, wrapped or containerized immediately upon removal. The personal and waste decontamination enclosure systems and floor and scaffold surfaces shall be HEPA vacuumed and wet cleaned at the end of each work shift at a minimum.

(2)Visible accumulations of asbestos-containing waste material shall be containerized utilizing non-metallic dust pans and non-metallic squeegees or HEPA vacuums.

(3)Metal shovels shall not be used to pick up or move accumulated asbestos-containing waste material or any other debris in the vicinity of isolation or surface barriers.

(b)The waste decontamination enclosure system shall be wet cleaned twice using wet cleaning methods upon completion of waste removal. When the worker decontamination enclosure shower room alternates as a waste container wash room, the shower room shall be washed immediately with cloths or mops saturated with a detergent solution prior to wet cleaning.

(c)The worker decontamination enclosure system shall be wet cleaned / HEPA vacuumed, as appropriate, after each shift change and meal break.

(d)If there is free standing water or if flooding occurs in the work area, work must stop until the water is collected and safely and properly removed. (Amended City Record 12/7/2018, eff. 1/6/2019)

Common Questions

Our team

Meet the people you will work with

Free case review

Talk to an attorney before you act on NYC code.

Free 15-minute case review with the attorney handling your matter. Same-day response during business hours across all five boroughs — OATH hearings, Housing Court, and real estate closings.

Or email us

[email protected]

An attorney reads every message.

  • Same-day response

    During business hours

  • Direct attorney access

    Same lawyer from intake to close

  • Flat-fee pricing

    On most OATH and closing matters