What is NYC RCNY § 4-12?

Quick Answer

(a) Definitions. Sprayed-on fireproofing materials.

General informational summary. Not legal advice for your situation. Consult an attorney before acting on any specific matter.

Michael Nacmias - Founding PartnerMichael Sargo - Partner
From the team atNacmias Law Firm, PLLCBrooklyn-based attorneys representingproperty owners across all five boroughsMeet the team →

§ 4-12 Application and Protection of Sprayed-on Fireproofing.

RCNY § 4-12

(a)Definitions. Sprayed-on fireproofing materials.

(1)Type I – Cementitious material with aggregate.

(2)Type II – Intumescent Mastic with fillers drying to a hard finish.

(3)Type III – Mineral fibers with inorganic binders.

(b)All sprayed-on-fireproofing of any type heretofore or hereafter approved by the Board shall, in addition to being installed in accordance with its specific approval, be further governed by the following requirements: (c) Surfaces to receive sprayed-on-fireproofing shall be cleaned of dirt, grease, oil, loose paint, and any extraneous materials immediately prior to the application of fireproofing.

(d)When used to fireproof columns, all types shall be permanently jacketed or otherwise protected from abrasion or displacement for the full height of the exposed column, but such protection need not extend more than 9'-0" above floor level.

(e)When used to fireproof beams and/or floor or roof construction, and when the lower flange of the beam or the bottom plane of the floor construction is less than 9'-0" clear to the floor below, Types I and III shall be permanently protected either by a suspended ceiling, or by other means such as mesh screening so as to prevent damage to or displacement of the fireproofing.

(f)The material used for the protection of sprayed-on-fireproofing shall be adequate for its purpose as approved by the Department of Buildings.

(g)Type III finished fireproofing shall be tamped to a uniform thickness which shall be not less than that approved for the required fire resistive rating.

(h)Types I and II finished fireproofing shall be of a uniform thickness which shall be not less than that approved for the required fire resistive rating.

(i)The general contractor and the owner shall provide qualified personnel to supervise the application of the sprayed-on-fireproofing. They shall certify to the Department of Buildings that the finished fireproofing of the completed building is in full compliance with the requirements of the approval granted, these rules and the drawings approved by the Department of Buildings. (Renumbered City Record 4/4/2019, eff. 5/5/2019)

Common Questions

Our team

Meet the people you will work with

Free case review

Have a matter that touches § 4-12?

Free 15-minute case review with the attorney handling your matter. Same-day response during business hours across all five boroughs — OATH hearings, Housing Court, and real estate closings.

Or email us

[email protected]

An attorney reads every message.

  • Same-day response

    During business hours

  • Direct attorney access

    Same lawyer from intake to close

  • Flat-fee pricing

    On most OATH and closing matters