What is NYC RCNY § 25-251?

Quick Answer

(a) Where buildings are vacant, unguarded, open to unauthorized entry and are required to be sealed by the provisions of an unsafe building order, they shall be sealed and protected in the following manner: (1) Buildings with exterior walls constructed of brick or other masonry. (i) All exterior openings including doo

General informational summary. Not legal advice for your situation. Consult an attorney before acting on any specific matter.

Michael Nacmias - Founding PartnerMichael Sargo - Partner
From the team atNacmias Law Firm, PLLCBrooklyn-based attorneys representingproperty owners across all five boroughsMeet the team →

§ 25-251 Sealing and Protection of Vacant and Unguarded Buildings.

RCNY § 25-251

(a)Where buildings are vacant, unguarded, open to unauthorized entry and are required to be sealed by the provisions of an unsafe building order, they shall be sealed and protected in the following manner: (1) Buildings with exterior walls constructed of brick or other masonry.

(i)All exterior openings including door openings, in the cellar, in the story at street level, in the second story above street level, on the course of a fire escape, or which are less than 12 feet measured horizontally from an opening in an adjoining building, shall be sealed with concrete block. One door opening, readily visible from the street, may, at the discretion of the owner, be sealed with a door. The door shall be of solid wood covered with 26 gauge metal or constructed of 1-inch by 6-inch tongue and groove boards with cross and diagonal battens of 1-inch boards and covered on the outside with 26 U.S. gauge galvanized steel with edging turned over and nailed with flat heads galvanized nails. The door shall be hung in such a manner that no screws are exposed on the outside of the door on either the hinges or the hasps. Hinges shall not have removable hinge pins. Two hasps and locks shall be provided, located so as to divide the height of the door in equal sections.

(ii)Concrete block shall conform to the provisions of Reference Standard RS-10 of the Administrative Code.

(iii)All door and window frames shall be removed before concrete blocks are installed. Brickwork which new concrete blocks will abut, shall be cleaned and thoroughly wetted before blocks are installed.

(iv)Doors and windows, not exceeding 6 feet in width, shall be sealed with concrete block at least 4 inches in thickness. Openings exceeding 6 feet in width shall be sealed with concrete blocks at least 8 inches in thickness.

(v)Concrete blocks shall be laid in masonry cement mortar with a mix of not more than three parts of sand for each part of masonry cement by volume. Joints in masonry shall be broken. Masonry cement shall conform to the provisions of Reference Standard RS-10. Joints on the exterior faces shall be struck and shall be provided with a smooth finish.

(vi)Openings in masonry walls, which are not required to be enclosed with concrete block in accordance with subparagraph (i) of paragraph (1) of this subdivision, shall be sealed with boards covered by sheet metal in the manner specified in paragraph (4) of this subdivision.

(2)Buildings with exterior walls constructed of material other than masonry.

(3)Openings in roofs shall be sealed as follows: (i) Roof bulkheads, skylights, ventilating equipment and similar structures shall be completely removed. Openings remaining after removal of structures shall be sealed with 1-inch tongue and groove boards, not less than 6 inches in nominal width, laid on 3-inch by 6-inch joists, not more than 16 inches on center. Joists shall be secured to the roof timbers framed about the openings in a sound and secure manner. Boards shall be covered with roofing to provide a watertight durable cover.

(4)Sealing of openings by boards covered with sheet metal, where permitted under subparagraph (vi) of paragraph (l) in masonry walls and under subparagraph (i) of paragraph (4) in walls of material other than masonry, shall be done in the following manner: (i) Boards shall be 1-inch by 6-inch cut to a length to fit the height and width of the wall opening, with a cross and diagonal battens of l-inch boards, on the inside, or shall be exterior grade plywood, at least 5/8 inches in thickness, cut to fit the wall opening on the inner side of the window frame.

(5)Utilities and service lines. All gas, electric, water, steam and other service lines to the building except sewer lines shall be disconnected and certifications to that effect by the respective utility companies or city agencies having jurisdiction shall be filed with the department.

(6)Prior to the completion of required sealing of exterior openings as detailed pursuant to paragraphs (1), (2), (3) and (4), above, all combustible debris, rubbish, abandoned furniture or materials capable of supporting combustion shall be removed from the premises.

Common Questions

Our team

Meet the people you will work with

Free case review

Have a matter that touches § 25-251?

Free 15-minute case review with the attorney handling your matter. Same-day response during business hours across all five boroughs — OATH hearings, Housing Court, and real estate closings.

Or email us

[email protected]

An attorney reads every message.

  • Same-day response

    During business hours

  • Direct attorney access

    Same lawyer from intake to close

  • Flat-fee pricing

    On most OATH and closing matters